The 2025 ISGP took effect January 1, 2025. Existing permittees had to update their SWPPPs on or before May 15, 2025 and implement the updates no later than July 1, 2025. If your SWPPP hasn't been updated since then, it is out of date. These are the requirements we see come up most on site, taken from the permit itself.
SWPPP and BMPs
- Keep all dumpsters under cover or fit them with a storm-resistant lid that stays closed when not in use
- Inspect equipment and vehicles for leaking fluids during monthly site inspections
- Each monthly inspection verifies that the SWPPP site map reflects current conditions
- Keep all BMP maintenance records
Training
Employees and contractors or vendors with duties in industrial areas must be trained within 90 days of hire. Part-time and seasonal employees, contractors and vendors must be trained within 30 days of hire. Everyone is retrained at least once a year.
Sampling and inspections
- Visual inspections every month, with at least one week between inspections
- Sample each designated location at least once per quarter
- pH must be measured with a calibrated pH meter accurate to 0.1 standard units
- Certain industries add 6PPD-quinone and PFAS sampling (see our PFAS and 6PPD-quinone guide)
Corrective actions
- Level 1: a benchmark exceedance in any quarter of the calendar year
- Level 2: exceedances in any two quarters of a calendar year, tallied facility-wide
- Level 3: exceedances in any three quarters of a calendar year, tallied facility-wide. The engineering report is due no later than six months after the end of that calendar year
Reporting
- Quarterly DMRs: Q1 by May 15, Q2 by August 15, Q3 by November 15, Q4 by February 15
- Annual report by May 15
- Annual Gross Revenue Form by March 15
Conditional No Exposure
Ecology responds to Conditional No Exposure exemption requests in writing within 90 days, and CNE status must be reapplied for every five years.
Sources: 2025 ISGP with errata; Washington Department of Ecology. This is a summary; your permit coverage letter and the permit text control.