Level 1, 2 and 3 corrective actions
When sampling results exceed benchmarks, the ISGP sets a corrective action level with its own deadlines. We prepare the response, track the dates and keep it documented.

Feb 15 Q4 DMR due: check results against benchmarks 81 days left
Then May 15 Q1 DMR due: check results against benchmarks · Jun 30 Level 3 engineering report due, if Level 3 was triggered last year

Full 12-month calendar
Starting November 2026, updated daily. Filing = a report is due. Sampling window = last day to collect a required sample. Event-triggered = only applies if something happened. Dates on a weekend or holiday can shift, and your coverage letter or agent may set site-specific dates.
November 2026
- 15 Filing: Q3 DMR due: check results against benchmarks
December 2026
January 2027
February 2027
- 15 Filing: Q4 DMR due: check results against benchmarks
March 2027
April 2027
May 2027
- 15 Filing: Q1 DMR due: check results against benchmarks
June 2027
- 30 Filing: Level 3 engineering report due, if Level 3 was triggered last year
July 2027
August 2027
- 15 Filing: Q2 DMR due: check results against benchmarks
- 31 Filing: Level 2 source controls due, if Level 2 was triggered last year
September 2027
- 30 Filing: Level 3 revised SWPPP fully implemented, if Level 3 was triggered last year
October 2027
Source: 2025 Industrial Stormwater General Permit (Ecology).
The requirement
Under the ISGP, benchmark exceedances for a single parameter, tallied facility-wide, trigger corrective action. Level 1 (any quarter) calls for an inspection and operational source control review. Level 2 (two quarters in a calendar year) calls for structural source controls in place by August 31 of the following year. Level 3 (three quarters) calls for treatment: an engineering report due June 30 of the following year when treatment needs site-specific design, and the revised SWPPP fully implemented by September 30 of the following year (Conditions S8.B to S8.D).
Who it applies to
ISGP facilities whose sample results exceed a benchmark.
What's included
- Level 1: source control and operational BMP review, with the SWPPP updated
- Level 2: structural source control BMPs and the required report
- Level 3: treatment BMPs, coordinated with a licensed engineer for the engineering report
- Natural background or off-site source investigations and technical reports
- Deadline tracking and the documentation for your annual report
Where we stop
We are compliance consultants, not engineers. When your permit requires a PE-stamped engineering report or treatment design, we bring in a licensed engineer and manage the process with you.
Common questions
What triggers a corrective action?
Under the 2025 ISGP, a benchmark exceedance in any quarter triggers Level 1. Exceedances in any two quarters of a calendar year, tallied facility-wide, trigger Level 2, and any three quarters trigger Level 3, which needs an engineering report within six months after the end of that year.
How are Level 2 and Level 3 triggered?
Level 2 is triggered by exceedances for the same parameter in any two quarters of a calendar year; Level 3 by any three quarters.
When is a Level 3 engineering report due?
No later than June 30 of the year after the Level 3 was triggered, when the treatment needs site-specific design (Condition S8.D). It must be certified by a licensed professional engineer, and we work with one. The revised SWPPP must be fully implemented by September 30 of that year.
What if the exceedance isn't from our site?
If it comes from natural background or an off-site source, we prepare the technical report that asks Ecology for relief.
Sources
Checked against these agency documents on November 26, 2026. Reviewed by Jason Ghaffari, CPSWQ, CHMM on November 26, 2026. Your permit and the agency are the final word.
Start with the lab result that exceeded the benchmark
Email us the lab result that exceeded the benchmark, and where the site is. We reply within one business day.